0G7A3761
Storage tank with a capacity of 120,000 gallons at the Reverse Osmosis (RO) Plant in Waterford.

(North Eleuthera, Bahamas)  — Chairman of the Water and Sewerage Corporation, Adrian Gibson led a delegation of senior government officials on a tour of several water plants in Eleuthera, on Thursday, May 16, 2019.

The first stop was to view the Reverse Osmosis (RO) Plant in Waterford, which services 800 customers in four settlements. The plant also features a storage tank with the capacity of 120,000 gallons as back up for up to four days.

“In addition to supplying water to these communities, we are hoping to tie in this plant to the Tarpum Bay plant in order to facilitate a more efficient water supply system,” said the Chairman, adding that improvement of services on the island is in keeping with the Government’s objectives of supplying optimal water services.

He said that the Corporation is also preparing for the impending Disney project.

Following the stop in Waterford, the delegation visited a storage and distribution facility in Bannerman Town. The system, which is a gravity fed pressure pump, supplies 25 households with potable water and features two storage tanks, each with a 5,000-gallon capacity.

0G7A3857
Chairman of the Water and Sewerage Corporation, Adrian Gibson led a delegation of senior Government officials to Eleuthera on Thursday, May 16, 2019. The delegation visited several water plants throughout Eleuthera including plants in Waterford, Bannerman Town and Lower Bogue. They also visited Harbour Island to inspect the removal of a cast iron pipe to PVC installation. (BIS Photos/Patrick Hanna).

“Systems such as this one reduces complaints of low pressure and inadequate supply,” said Mr. Gibson. “We put this type of mechanism in place to serve smaller communities such as Bannerman Town.”

The Chairman also visited an RO plant in Lower Bogue. He said it is the largest of its kind on any island outside of New Providence. The plant has the capacity to supply 500,000 gallons of water daily to customers. He said that construction commenced in October 2018 and it is anticipated that it will come to completion soon.

The delegation also made a stop to Harbour Island and Spanish Wells. On Harbour Island, remedial works had been carried out to remove 600-feet of cast iron pipes to PVC pipes. The Chairman said that this was done to respond to complaints of brown water.

Member of Parliament, the Hon. Ricardo Mackey, also toured the Harbour Island site with the Nassau delegation. He said he was pleased that the Corporation has been able to resolve the issues.

0G7A3891
Member of Parliament for North Eleuthera, Mr. Rickey Mackey, touring works done in Harbour Island with Water and Sewerage Corporation Chairman, Mr. Adrian Gibson, and his delegation on Thursday, May 16th, 2019.

“The issue of brown water has been a legacy problem for some time,” said Mr. Mackey. “This new RO system has addressed the problems of brown water and low pressure, and accessibility has been greatly improved. Brown water is now a thing of the past. The population of Harbour Island stands at approximately 2,500 year round and 4,000 persons during the winter months when there is an influx of visitors and transient residents.”

 

By: Betty Vedrine